Indurent Park Access 18 – Avonmouth

We are pleased to confirm the successful completion of another project for our Construction division, delivering a 215,000 sq ft warehouse and office development for Indurent Park, Access 18 in Avonmouth. The scheme was completed to a high standard and handed over on programme within a 44-week construction period.

The development includes a warehouse with integrated office accommodation, comprising 23 dock levellers, 37 trailer bays and 192 car parking spaces, alongside EV charging, PV provision and FWPs. The works also involved extensive ground improvement, piled foundations and slab construction, together with associated culverted highway access works, yards, and soft and hard landscaping.

Project highlights:

  • 44-week construction programme

  • Over 100,000 work-hours delivered

  • More than 1,200 site inductions completed

Working in close collaboration with our trusted supply chain, the project was delivered efficiently and safely, reflecting the collective expertise and commitment of everyone involved.

A great example of the Barnwood team delivering large-scale industrial schemes for clients such as Indurent, with expert craftsmanship, collaborative delivery, and focus on quality and programme.

Photography – Time Lock Photography

Drone Footage – Andrew Walker, Site Manager